All ideas
Site Diary Form do not link correctly for a report when there are multiple work fronts.
The key items for a good report is General information (add site / reported by, total people onsite. WBS/Work package/ Description 2.1 Contractor/ Sub. 2.2 Site Activities:(Description Box) Scope % complete/ Breachs /Discussions/ Work Instructions / NCR / Plan for next day / Photos (Check box for N/A or Nil) 2.3 Labour - Labour Type / Qty. (Dropdown box & +add EG. Riggers 2, Crane Operators 1, Boilermakers 2) 2.4 Equipment & Machinery - Type / Qty / Hrs worked / Photo (Dropdown box and +add 2.5 Materials Delivered - Same as your form add a photo at the bottom of the materials as evidence Add next package + Add ( Status